Clermont-Ferrand 2 / France

CHU (01)

 

CHU (02)

 

CHU (03)

 

CHU (04)

 

CHU (05)

 

CHU (06)

 

CHU (07)

 

CHU (08)

 

CHU (09)

 

CHU (10)

 

Location:

Clermont-Ferrand 2 / France

 

 

Start of construction:

August 2011

 

 

Acceptance by power supply company:

February 2012

 

 

Installed performance:

ca. 1.488 kWp

 

 

parking space surface / modules:

ca. 23.700 m² / 7.833 modules

 

 

Project description:

  • Roofed parking system on hospital site
  • Bearing structure system: W-structure for two-row parking places and X-structure for one-row parking places
  • Hight under roofed parking system: ca. 3,50 m - 5,30 m
  • Roof pitch: 10°

 

 

Individual services:

  • Excavation works  and foundation including driven foundation piles, anchor plates and reinforcement structures
  • Installation of temporary parking area during works
  • Conversion of existing parking area (e.g. new exit of parking area, marking of parking places, drainage system)
  • Installation of steel bearing structure
  • Installation of modules in supporting frame structure (steel or aluminium)
  • Complete cabling on low and medium voltage side including the installation of the inverter station and generator connection box
  • Installation of lighting

 

 

 


print